How can I sync Task Duration & Task Effort info with MS Outlook (365)

Kjell-Tore E. shared this question 2 years ago
Discussion Open

When syncing Tasks wo Outlook, info on Task Duration and Task Effort seams not to be stored anywhere in the Outlook task, and Task Total Work & Actual Work info in Outlook task is not shown anywhere in MindManager. This limits the potential use of MindManager as a planning tool for Outlook tasks.

Are there any workarounds for this? Adding and using a custom field in Outlook is acceptable (though not optimal).

Replies (1)

photo
1

It works for me.

Maybe you've installed different bit-version. Outlook and MindManager have to be installed with the same bit-version. Otherwise the Outlook Sync doesn't work.