Parent task not reflecting completion of child tasks
Answered
I have encountered this issue a few times, and can't figure out the issue.
Despite having all children tasks showing 100% Progress, the parent task does not reflect completion. The progress at the parent level seems disconnected from the child, and all the task info is greyed out, indicating that it cannot be updated manually.
I guess MindManager is calculating the rolled-up progress by adding up effort x progress, then dividing by total effort. As the total effort is 0, this results in divide-by-zero which returns as 0.
I guess MindManager is calculating the rolled-up progress by adding up effort x progress, then dividing by total effort. As the total effort is 0, this results in divide-by-zero which returns as 0.
Switch on the roll up tasks option in the define taskinfo window
Switch on the roll up tasks option in the define taskinfo window
It looks like the tasks are milestones.
If this is true I would expect the result you have.
It looks like the tasks are milestones.
If this is true I would expect the result you have.
---