Automatic scheduling does not work

Josephus shared this question 2 years ago
Discussion Open

I use MM 22. I created a few tasks with a finish to start dependency. In one case, two subsequent tasks do not follow one after the other: some delay is introduced. I removed the slack, to no avail. The first task ends at 10:15. The second should therefore start at the same time. It starts at 11:00. It is not even possible to overtype the starting time. What is going on here?

Replies (1)

photo
1

What units are the task durations defined in? Tasks with the duration specified in hours will start on hour boundaries. To start tasks on a minute boundary the task duration must be specified in minutes.

---