Is it possible to synchronize resources over linked maps
Discussion Open
When sending a Topic to a new map ( linked map ) all resources is copied to the new map.
But afterwards, there is no synchronization of the resources ( or tags ) why is that ?
Is it possible to set this up somewhere in the settings, to ensure that all resources always stay synchronized and part of the roll up feature in the "main" map ?
Only if the mind maps are linked via Map Roll Up will changes from one map be transferred to the other, e.g., resources.
If you make any changes in the linked map, they will also be displayed in the second map.
Only if the mind maps are linked via Map Roll Up will changes from one map be transferred to the other, e.g., resources.
If you make any changes in the linked map, they will also be displayed in the second map.
Thank you for replying to my question
What i'm in need of is "people" resources syncronizing between Main map and Sub map(s)
I have a (main) map with all my coworkers as "people" resources, maintained in resource manager I want to syncronise all these resources to a sub map. A colleague, maintains that sub map, and assigns tasks to "people" resources. Sometimes he create a new resources, emploees that havent been assigned at tast before.
The problem is that the main map "dashboard" will not have these "new people" resources syncronised back.
Is it possible in some way to do that ?
Thank you for replying to my question
What i'm in need of is "people" resources syncronizing between Main map and Sub map(s)
I have a (main) map with all my coworkers as "people" resources, maintained in resource manager I want to syncronise all these resources to a sub map. A colleague, maintains that sub map, and assigns tasks to "people" resources. Sometimes he create a new resources, emploees that havent been assigned at tast before.
The problem is that the main map "dashboard" will not have these "new people" resources syncronised back.
Is it possible in some way to do that ?
Syncronization in both directions is not possible.
Is it about resource planning in your projects? Or are other people planning and you just want an overview?
Syncronization in both directions is not possible.
Is it about resource planning in your projects? Or are other people planning and you just want an overview?
---