How to manage Baseline in Mindmanager

Darren shared this question 11 months ago
Discussion Open

How to manage the project in Baseline,How do you know if you're late in a speciale date of scheduling.

Best Answer
photo

If the project manager enters changes in the plan, such as a longer duration, and the task is completed later, it does not work. One possibility would be to set a property [planned end] and insert a smart rules. The flag shows the status. afc44c85be84d31b82f981bdb76f8099

9faf1c32ab9e2796b1ae3e9e0c41e94e

5e29458ada478cc7438a7779740cce3a

4360f5595c0bc7bd7a1f193035f029a7

Replies (1)

photo
1

MindManager does not support project baselining, but you can set due dates on tasks and it will automatically display whether a task is at risk or overdue using Smart Rules.

You can set dependencies between tasks, but due dates are automatically moved back when the project network is rescheduled. The map is a snapshot of progress against the current schedule, but the schedule itself is dynamic, meaning you need to verify task statuses if you use dependencies. There is no baseline reference stored anywhere.

One approach is to use a few Milestone tasks with well-known target dates and keep an eye on these. You could include the target date in the topic text for clarity, e.g., "Conference preparations complete by 2/7/23", making it easier to compare against the currently scheduled due date and progress.

photo
1

Thank you Nick.

photo
2

If the project manager enters changes in the plan, such as a longer duration, and the task is completed later, it does not work. One possibility would be to set a property [planned end] and insert a smart rules. The flag shows the status. afc44c85be84d31b82f981bdb76f8099

9faf1c32ab9e2796b1ae3e9e0c41e94e

5e29458ada478cc7438a7779740cce3a

4360f5595c0bc7bd7a1f193035f029a7

photo
1

Someone help me to have this in english

photo
2

Hi Darren,

I hope it helps you

my proposel 



photo
1

Thank you

---