Hello,
I would like to set a dependency between two tasks:
as soon as task 1 ends, task 2 shall start. This dependency shall be automatically updated, If I change the duration of task 1.
Currently, If I reduce the duration of task 1, task 2 start date stays the same.
This is very annoying, because the overall project time stays the same, and i have to check everything again manually, if there is any gap.
I'm using Enterprise version 20.1.231
THX for you help
Files:
MinmanageStartD...
The "remove slack" button might help. If your project isn’t too complex.
The "remove slack" button might help. If your project isn’t too complex.
Hi Botond,
you're using the wrong dependency. It hast du be "Finish to Start".
But you still have to remove the puffer. Puffer-time is needed in projects and therefore the are not removed automatically.
Best, Andreas
Hi Botond,
you're using the wrong dependency. It hast du be "Finish to Start".
But you still have to remove the puffer. Puffer-time is needed in projects and therefore the are not removed automatically.
Best, Andreas
Thank you all for the fast responses.
These helped. To apply both tips, were needed.
Thank you all for the fast responses.
These helped. To apply both tips, were needed.
If you have mm enterprise you need to have MSA so you are entitled to the latest version ( 21 for windows) Talk to your system admin about the upgrade.
If you have mm enterprise you need to have MSA so you are entitled to the latest version ( 21 for windows) Talk to your system admin about the upgrade.
---