Gantt pro personalization

Giorgia L. shared this question 23 days ago
Answered

Is it possible to personalize the Gantt pro? In particular:

- Change dependencies format (color / shape)

- Put all the milestones on the same line

Replies (2)

photo
1

Short answer: NO

The colour of the bars is taken from the branch fill colour from the map. More is not possible.

photo
1

By definition, a Gantt chart has one task per line. But if you assign all Milestones to the resource "Milestone", then the Resource Chart will show them all on a single line next to the Milestone resource, with individual milestones detailed below each box.