How to filter for undone tasks?

David S. shared this question 7 months ago
Answered

I am using Mind Manager 23 on Mac (mainly the desktop version) for task tracking, along with many other things.

I want to filter large task files to show only tasks that are not yet done - that is, "percent complete" does not equal "done." I can create a filter like this easily, but it doesn't work. I have contacted technical support, and I was told that there is no ETA for resolving this issue.

Does anyone know of a "work around" that will allow me to see only tasks that are not complete?

Replies (2)

photo
1

I quickly implemented my idea in MM Win. I can't say whether it works for MM Mac.

The first workaround works with a property and a formula

Another workaround would be to assign a tag for branches that are not finished and then filter them.

I quickly took the pictures in the German version. I hope it is understandable

e0165c9c5e0f0468d764ef527018c125

d4e11764f3c991f1c1c6aca5336e0369

photo
1

Hello David,

I second René's suggestion to use a SmartRule. Create a SmartRule where the trigger is Task Progress - Is Less Than - Done

and choose an effect.

Best regards,

-Marian