Several resources on one task with different effort
Answered
I have different resources working together on a task but with different effort:
e.g. Resource A: 8h
Resource B 2h
Can I divide this up sensibly without having to define 2 tasks for it?
Thanks in advance for your help.
Best regards
Peter
Hi Peter,
you can change the effort in Gantt Pro Chart.
Open the task in the Gantt Chart and change the effort in the resource tab.
Hi Peter,
you can change the effort in Gantt Pro Chart.
Open the task in the Gantt Chart and change the effort in the resource tab.
Thank you so much René! You are my Hero of the day!
@MindManger: It would be nice if it were possible to do this directly in the Task tab without defining the date. Because in an iterative planning mode, I start with the effort per person, check the availability according to the effort and then define the dates.
Best regards
Peter
Thank you so much René! You are my Hero of the day!
@MindManger: It would be nice if it were possible to do this directly in the Task tab without defining the date. Because in an iterative planning mode, I start with the effort per person, check the availability according to the effort and then define the dates.
Best regards
Peter
Hello Peter
You can also right-click on the resource tag in the topic itself (e.g. "Heidi" or "Paul" in René's example), and click "Edit Resource Effort". This allows resource efforts to be defined within the map without using the Gantt chart.
Hello Peter
You can also right-click on the resource tag in the topic itself (e.g. "Heidi" or "Paul" in René's example), and click "Edit Resource Effort". This allows resource efforts to be defined within the map without using the Gantt chart.
Thank you Nick. That´s what I was looking for!
Best regards
Peter
Thank you Nick. That´s what I was looking for!
Best regards
Peter
---