Move a Task up or down in Gantt Chart view

Thomas F. shared this question 2 months ago
Answered

This seems easy but I'm not finding where to move a task up or down within a Gannt Chart. MM is saying its not an options. Seems like it would definitely be an option.. but, maybe not.

Replies (3)

photo
1

I think you could do this only directly in the map

photo
1

The order of tasks in the Gantt chart can be either in map order, or in start date order. This is set in the Gantt options.

photo
1

Looks like you can do it in map view. Thanks

Leave a Comment
 
Attach a file