Can task's duration by default be in hour not workday? thx

krsto e. shared this question 11 months ago
Answered

i only use for personal work,

but i wish to use hour and not workday for some reason.

it's workday now by default.


i am on mindmanager 2020, thanks


3b140dd4241bcba125a6a8bb9b0b3f36

Replies (2)

photo
1

If you uncheck the box you can change the unit
                
photo
1

If you assign a Resource to the task, the Effort will be calculated in hours, or minutes if it is not a round number.

As Jörg says, un-checking the checkbox that links Duration and Effort will allow you to put any number or unit in the Effort field. It will just be a number, unrelated to the Duration and Resources for the task.

---