Is it possible to fix a milestone in the mind manger program?

Daniel R. shared this question 14 months ago
Answered

Is it possible to fix a milestone!
It should not move anymore even if dependencies have been defined.
Is it possible?

Replies (2)

photo
1

Hello Daniel. This is not a feature today, but there are some workarounds:

  • You can create a SmartRule on a topic that will set an icon or change fill colour if it is scheduled past a fixed date.
  • You can also plan backwards from a fixed project end date by moving the end date in the Gantt window,

photo
1

Hello Nick

Thank you for the feedback.

But unfortunately these are not the solutions I need.
I have the problem that when I have linked dependencies and appointments move, all appointments move with them, so a colour or something similar doesn't help me.

It is a pity that this is not possible!
SG Daniel

---