Dependencies
Answered
Hello,
What controls dependencies to be red or black, se picture
/Jon
Files:
2022-06-28_07-3...
Hello,
What controls dependencies to be red or black, se picture
/Jon
Tasks connected by red dependencies are on the "critical path". A task on the critical path directly influences the overall project length. If the task is late or extended, the project will be late or extended.
Tasks connected by red dependencies are on the "critical path". A task on the critical path directly influences the overall project length. If the task is late or extended, the project will be late or extended.
---