How can I get an individual effort on a task ?

Christian H. shared this question 36 hours ago
Discussion Open

Hi all,


I have a task with several people assigned to it, each people having different efforts.

How can I get the individual effort of each people in this task ?


Thank you

Replies (1)

photo
1

Hi Christian,

2 settings:

weekly working hours

and percentage availability for the project