How to reoder the task in the Gantt Pro view?

Tian shared this question 12 days ago
Discussion Open

When we enter into the Gantt Pro view, the tasks are automatically shown in the order that its topics are created. Is there a simple dan direct way to reoder the tasks?

523d95ade5deebafaf955938ff59bcdf770336f53db95af18e7265717ae56238

Replies (1)

photo
2
  • Click the "Options" button
  • Un-check the checkbox "Use the default options for this map" so that this map has its own options
  • Change the option at the bottom of the dialogue from "Sort chart by map order" to "Sort chart by start date". Sorting by date is the usual convention for Gantt charts.

Leave a Comment
 
Attach a file
You can't vote. Please authorize!