RE: Serial/Sequential arrangment of tasks in MM23 Ghatt view HTTP5 view

Jack O. shared this question 45 days ago
Answered

Dear Team,

Please, look at the Ghantt view below and advise me on how I can arrnage the tasks Serially/Sequentially

https://share.mindmanager.com/#publish/eVOpdWL3A_-f7LSWdRq8W7HDrIbn8pWR8q4GG7VN

I am using MindManager 23.

Kind regards, Jack

Replies (1)

photo
1

Could you please explain that a little more? Do you mean to show the tasks in a dependent relationship?
Like this

6ba66c9194bc7ff4d9708bb59863141470d9b15cb10724b8f5a10e6752a1588b

photo
1

No. In MM23, the Taska are nto orgzinzed sequentially. How do you organize serially/sequentially?

photo
1

Select the branches, and then select the dependency in the task information.

c62bcc0aaf4226693fd18f8c3c4b244f8788ad3f101c57560ce07d33c962a7fe

photo
1

Also important: The “work” branch does not have its own duration or effort.

“Roll Up” must be selected for the branch

af59cb360f9d7e0662cc91681eb4bbb651c745b39c67924cc5d35de54f12adf2

photo
1

Thanks