Improvement Suggestion - Gantt Chart - Task Attributes - Critical Path Calculations
                
                Voting Open
            Hi Gang,
Not sure if this is the correct place to propose a product improvement opportunity or not?
I'm starting to utilize Mind Manger for some project work. As the projects develop I'm interested in identifying the Critical Path. I noticed that with the current Gantt Chart we are not able to set some basic Gantt Chart attributes of Tasks:
- As late as possible
 - As soon as possible,
 - Finish no earlier than
 - Finish no later than
 - Start no earlier than,
 - Start no later than.
 
As you can see in the chart below, I've set a Finish to Finish (and the Task can finish as late as possible), yet it is pushed to the Left and identified as currently on the critical path
 
Cheers,
Richard.